The shares of this company are engaged in the construction of dams, bridges, tunnels, roads, piling works, industrial structures and other kinds of heavy civil engineering works in areas like hydro, irrigation & water supply, urban infrastructure and transport are in the spotlight after it rose by 7 per cent in today’s market session following its emergence as the lowest bidder for a Rs. 1,441.04-crore hydroelectric project in Arunachal Pradesh. 

With a market capitalisation of Rs. 2,368 cr, the shares of Patel Engineering Ltd were trading at Rs. 23.87 per share, increasing over 7% in today’s market session, making a high of Rs. 24.66, up from its previous close of Rs. 23.01 per share. 

Also Read: Sensex & Nifty 50 | Stock Market Live Updates Today: Sensex Closes 0.46% Higher, Nifty 50 Gains 0.25% as IT Stocks Rally 3.66%

About the order 

Patel Engineering Ltd has been declared the lowest bidder (L1) by Dirang Energy Private Limited (DEPL), its wholly owned subsidiary, for the execution of the 144 MW Gongri Hydro Electric Project in West Kameng district, Arunachal Pradesh. The project is valued at Rs. 1,441.04 crore, including GST, and is scheduled to be completed within 48 months from the date of award.

The project is a run-of-the-river hydroelectric development on the Gongri River, a tributary of the Bichom River in the Kameng basin. It will have an installed capacity of 144 MW, comprising two units of 72 MW each, and is designed to generate 623.19 million units of electricity annually. The project will be developed by DEPL on a Build-Own-Operate-Transfer (BOOT) basis for a 40-year lease period.

Also Read: Why Did Action Construction Equipment Shares Surge 8% Today? Here’s What Triggered the Rally

The contract includes construction of a diversion barrage, intake structures, desilting chambers, a 7.1 km head race tunnel, surge shaft, pressure shaft, surface powerhouse, tail race channel and switchyard. It also covers hydro-mechanical and electro-mechanical works. The project aligns with Patel Engineering’s established capabilities in hydropower and tunnelling, with the company having completed more than 85 dams, 40 hydroelectric projects and over 300 km of tunnelling.

Order Book 

Patel Engineering reported a total order book of Rs. 13,546.4 crore across 52 projects. Hydroelectric projects account for the largest share at Rs. 8,620.4 crore, contributing 63.64% of the total order book, followed by urban infrastructure and other projects at Rs. 2,262.1 crore (16.70%) and irrigation projects at Rs. 1,962 crore (14.48%). The remaining orders comprise tunnel projects worth Rs. 483.9 crore and road projects worth Rs. 218 crore. 

In terms of client concentration, Central Government and PSU projects contribute Rs. 8,453.1 crore, accounting for 62.40% of the total order book. State Government projects represent another Rs. 3,901.4 crore or 28.80%, while international projects contribute Rs. 393.7 crore. This indicates that the company’s order pipeline is largely dependent on government-funded infrastructure projects.

Also Read: BSE vs NSE: Which Stock Offers Better Growth Potential Amid Rising Market Share and Valuation Concerns?

About the company 

Patel Engineering is an engineering firm having more than 75 years of experience in the industry with more than 350 projects being executed by the firm such as constructing 87 dams and more than 300 km of tunnels. The projects have been successfully completed on hydro energy projects with a total capacity of more than 15,000 MW and the construction of more than 1,200 km of road and irrigation projects of more than 5.5 lakh acres. The firm has 52 projects under execution in 14 states in India as well as in Nepal and Bhutan.